Every 10 years or so, the American
Institute of Architects (the AIA)
revises its form construction documents.
Those revisions are typically
substantive and extensive, and the
latest revisions, the 2007 form
documents, are no exception. It is
therefore of critical importance that
all parties to construction projects,
owners, developers, construction
managers, contractors, and
subcontractors, carefully analyze the
new documents with their counsel and
make appropriate modifications before
signing them.
The matter is further complicated by the
fact that a new, competing set of form
documents has just been promulgated by
an organization called ConsensusDOCS.
The ConsensusDOCS form documents were
produced by a collaboration of 19
construction association groups,
including owners, contractors,
subcontractors, and others.
1
Both the AIA and the ConsensusDOCS form
documents are electronically available,
but can only be obtained by subscribing
to the respective organization's
service.
This article covers the new general
conditions form document promulgated by
the AIA, the AIA Document A201-2007,
first addressing some of the new rights
and obligations of the parties, then the
new disputes resolution provisions set
forth therein, and finally comparing the
A201-2007 disputes resolution provisions
to those of the new ConsensusDOCS
analog, the ConsensusDOCS 200.
The AIA Document A201
As was true for its 10-year-old
predecessor (the A201-1997), the new
A201-2007 form will serve as the general
conditions for a multitude of AIA form
construction agreements. These include
the newly promulgated A101-2007, the new
A102-2007 (previously, A111-1997), the
new A103-2007 (previously, A114-2003),
and the newly promulgated A401-2007. In
addition, the new version of another
frequently used AIA form document for
small projects, the A107-2007, contains
a number of general conditions
provisions that mirror some of the new
provisions of the A201-2007, although it
does not explicitly cross-reference that
form document.
New Rights and Obligations of
the Parties
The new A201-2007 imposes new
requirements on the construction manager
(CM) and general contractor (GC). These
new requirements tend to favor the
owner/developer vis-ŕ-vis the CM or GC.
Increased Rights Afforded the Owner:
• Owner's financing. Unlike the
procedure previously in effect, under
the new A201-2007, the CM or GC can no
longer request information about the
owner's ability to finance the project
at any time.
2 Instead, while
the CM or GC may so request prior to
commencement of the project, it may do
so thereafter only if (1) the owner
fails to make a payment required under
the Contract Documents, (2) a change in
the Work materially changes the Contract
Sum, or (3) the CM or GC "identifies in
writing a reasonable concern regarding
the Owner's ability to make payment . .
. ."
3 Although this revision
appears to benefit the owner/developer,
problems may well occur if payment
issues arise, a not-infrequent
occurrence on construction projects.
• Owner ability to issue joint checks to
contact subcontractors directly. A new
provision permits the owner to issue
joint checks to the CM or GC and its
subcontractor if the architect has
withheld a payment certification due to
a failure of the CM or GC to pay its
subcontractor(s).
4 In
addition, the owner now has the right to
request that the CM or GC provide
written evidence of proper payment to
its subcontractors and suppliers and, if
the CM or GC fails to provide such
evidence within seven days, the owner
may contact them directly.
5
These provisions will assist the
owner/developer in keeping its project
moving, even when its CM or GC is late
in paying its subcontractors. It also
permits the owner/developer a mechanism
for avoiding later liens from
subcontractors or suppliers with which
the owner/developer is not in
contractual privity.
New Duties of CMs and GCs:
• Review of contract documents and field
conditions. Previously, the CM or GC
could only be held liable to the owner
for failure to notify the owner or
architect of a nonconformance of the
contract documents if the Contractor "
knowingly
failed to report [such
nonconformance] to the Architect."
6
Under the new A201, mere failure to
report may give rise to liability.
7
This new provision will assist the
owner/developer in providing an
additional cause of action should
litigation arise. It also may prevent
later CM or GC claims predicated on
non-conforming or defective plans and
specifications.
• Differing site conditions. A new
provision requires the CM or GC to
notify the architect if it recognizes
"burial markers, archeological sites or
wetlands not indicated on the Contract
Documents."
8 Given that even
experts disagree as to whether certain
ground conditions can be so
characterized, this provision may prove
burdensome to the CM or GC.
• Project superintendent. New provisions
have been added requiring the CM and GC
to promptly notify the owner of the name
and qualifications of the proposed
project superintendent and not change
superintendents without the owner's
consent.
9 These provisions
are important to the owner/developer
because no matter how well-known the CM
or GC is, each construction project is
built by the individuals assigned to it
and the owner/developer has a reasonable
basis to want to know and have
confidence in the people so assigned.
• Submittals. Under the procedures set
forth in the new form, if the CM or GC
fails to submit a submittal schedule, it
will lose the right to claim any
monetary increase or time extension
required for review of submittals.
10
In addition, the CM's or GC's submission
of shop drawings and the like now
constitutes a representation that the CM
or GC has reviewed and approved them.
11
Both of these provisions are of benefit
to the owner/developer in seeing that
submittals are properly reviewed and
that the project proceeds with fewer
interruptions due to missing submittals
and the like.
Reduced Obligations of the
Architect:
• Architect's reporting duties. The
architect's site visits are no longer
"as a representative of the Owner" and
he/she will no longer "keep the Owner
informed" and "endeavor to guard the
Owner against defects and deficiencies
in the Work" as set forth in the prior
version, the A201-1997.
12
Instead, the architect will merely visit
the site "to determine in general if the
Work
observed . . . when fully
complete . . . will be in accordance
with the Contract Documents."
13
In addition, the architect is only
required to report "(1)
known
deviations from the Contract Documents
and (2) defects and deficiencies
observed in the Work."
14
If the owner/developer seeks greater
protection vis-ŕ-vis the architect, that
should be addressed in the separate
agreement with the architect.
New Provision Regarding Electronic
Communications:
• Electronic transmission of materials.
In recognizing the prevalence of e-mail
and electronic transmission of documents
generally, the new A201 requires the
parties to establish protocols for such
transmissions.
15
Dispute Resolution Process
The new A201's dispute resolution
procedures are far more complex than the
prior version, but also more flexible.
First, the aggrieved party presents its
claim to something new called the
Initial Decision Maker (the IDM). In the
past, the IDM was always the architect,
but now the parties may designate
someone else in the contract documents.
If one party is not satisfied with the
IDM's decision, that party may then
request mediation, but the procedure is
a strange one: either party must make
formal demand that the other file for
mediation and if not done, then that
other party waives its rights to mediate
or arbitrate/litigate the "initial
decision."
16 The effect of
this rather convoluted procedure, if not
modified by the parties, may be to allow
the winner to avoid mediation and even
arbitration/litigation. Counsel would be
therefore well advised to search the new
A201 carefully so as to ameliorate the
ramifications of such quirky provisions.
After mediation, the parties may then
pursue either arbitration or litigation,
depending on what they had agreed upon
in the originally executed agreement.
17
If arbitration was the method selected,
the new form permits something very
important that was not previously
permitted - consolidation with other
arbitrations provided three specific
criteria are met.
18
Possible Problems
•
With the A201's "Independent
Decision Maker"
In adding the IDM concept to the
disputes resolution process, the AIA
appears to be responding to criticism
that having the architect as the
decision maker in the first instance
tended to favor the owner/developer, its
client. In addition, the IDM concept
appears to be part of an overall trend
in the new AIA form documents generally
to shield the architect from liability.
As noted above, in the prior A201-1997,
the architect was in essence the IDM,
although in the new framework the
parties may still choose the architect
for that role. Assuming the parties
select someone else, the questions that
will arise from that selection are many:
To whom does the IDM report - the
owner/developer or the CM or GC? Who
pays for the IDM's services? Is the IDM
required to interpret the drawings? Is
the IDM qualified to do so, and doesn't
that impinge on the architect's
administration of the contract? What
immunity will the IDM have from suit?
What insurance will the IDM carry, if
any insurance can be obtained? None of
these questions is addressed in the
A201-2007 form itself, so the parties
must do so on executing their agreement.
Though by no means exhaustive, the
extensiveness of these questions, and
the fundamental nature of the issues
raised, shows that one should not
blindly sign any agreement that
incorporates the A201 by reference. The
parties and their counsel would be
well-advised to revise the new A201 form
before executing any agreement utilizing
it.
ConsensusDOCS 200
Clearly designed to compete with the AIA
A201-2007, the new ConsensusDOCS 200's
general conditions provisions differ
considerably from the A201's provisions.
Regarding disputes resolution, the
ConsensusDOCS 200 provides for a more
collaborative process, in three distinct
stages. Preliminarily, ConsensusDOCS 200
requires that during any dispute
situation, the Contractor continue
working and the Owner continue payments.
19
The first stage of actual dispute
resolution is direct discussions, first
at the field level, but if that does not
succeed within five days, at the senior
executive level. If those discussions
fail, the next stage is either
"mitigation" or "mediation," depending
on the choice agreed upon at the time of
executing the agreement.
20 If
no choice is made, the default procedure
is mediation.
21
The "mitigation" process set forth in
ConsensusDOCS 200 requires designation
of an independent Neutral or Dispute
Review Board (DRB), selected and paid
for by the parties equally.
22
That DRB is to hear the dispute and
render nonbinding findings within five
days of hearing. The ConsensusDOCS 200
states that the DRB's nonbinding
findings may be admitted into evidence
in a subsequent binding adjudication,
23
so the parties should seek to modify
this provision if that is not their
intention. In addition, distinct from
dispute resolution functions, if the
parties so request, the DRB may also
visit the project periodically
throughout the course of the project.
24
Such a function would only make sense on
relatively large projects, but would
certainly facilitate dispute resolution,
likely even preventing disputes from
occurring, another indicator that the
ConsensusDOCS 200 seeks to have the
parties act collaboratively.
Mediation, the default procedure for the
second disputes resolution stage, is
designated to be performed by the
American Arbitration Association, unless
the parties choose another organization
to do so, and there are several other
highly reputable mediation organizations
from which to choose. In order to
prevent the mediation from unduly
delaying a binding decision, there are
specific deadlines about completing the
mediation: it shall commence within 30
days and conclude within 45 days of the
issue having been raised.
25
In addition, at least under the American
Arbitration Association's rules for
mediation, the party requesting
mediation may commence arbitration
simultaneously with the mediation so as
to facilitate the former, just in case
it proves to be necessary.
26
The third stage, if neither mediation
nor mitigation has succeeded, is binding
litigation or arbitration, depending on
the parties' choice at the time of
executing the contract.
27
Although not specified in the
ConsensusDOCS 200, litigation would be
the default procedure, because parties
may not arbitrate without a written
agreement to do so. Additional
provisions worth noting: (1) joinder of
all necessary parties is required,
roughly analogous to, but more expansive
than, the A201 consolidation procedure,
and (2) the "non-prevailing Party" must
pay the costs of the adjudication, as
determined by the adjudicator.
28
With regard to the latter, the term
"costs" is not defined, so whether or
not it includes legal fees, and the
amount thereof, should also be presented
to the adjudicator for determination.
As noted, the ConsensusDOCS 200 form
appears to foster a more collaborative
relationship between owner and GC/CM
than does the new AIA A201, although
both forms will require a fair amount of
modification by counsel.
Conclusion
Given the complexities and changes set
forth in the new AIA Document A201-2007,
and the advent of the new, ConsensusDOCS
200, all parties to construction
agreements - owners, developers,
construction managers and contractors,
as well as architects - would be
well-advised to have their attorneys
carefully review the terms of the form
chosen.
Brian G. Lustbader,
counsel to Mazur, Carp & Rubin,
specializes in construction contract
negotiation and litigation. E-mail:
blustbader@mcrlawfirm.com.
Endnotes:
1. The acronym "DOCS" in the name "ConsensusDOCS"
stands for Designers, Owners,
Contractors and Subcontractors, although
I am not aware of any association of
designers or architects that has
participated in this collaboration.
Presumably, the architects and designers
work within the AIA.
2. AIA Document A201-1997, §2.2.1.
3. AIA Document A201-2007, §2.2.1.
4. Id., §9.5.3.
5. Id., §9.6.4.
6. AIA Document A201-1997, §3.2.3,
emphasis added.
7. AIA Document A201-2007, §3.2.4.
8. Id., §3.7.5.
9. Id., §§3.9.3, 3.9.4.
10. Id., §3.10.2.
11. Id., §3.12.6.
12. AIA Document A201-1997, §4.2.2.
13. AIA Document A201-2007, §4.2.2,
emphasis added.
14. Id., §4.2.3, emphasis added.
15. Id., §1.6.1.
16. Id., §15.2.6.1.
17. Id., §15.4.1.
18. Id., §15.4.4. Those criteria are (1)
the other arbitration agreement(s)
permit consolidation, (2) the
arbitrations involve common questions of
law or fact, and (3) the arbitrations
employ materially similar procedures.
19. ConsensusDOCS 200, §12.1
20. Id., §12.2.
21. Id., §12.4.
22. Id., §12.3.
23. Id., §12.3.
24. Id., §12.3.1.
25. Id., §12.4.
26. See R-9 of the American Arbitration
Association's Construction Industry
Arbitration Rules and Mediation
Procedures.
27. Id., §12.5.
28. Id., §§12.5.1 and 12.6.